Optical infrastructure of Almaty Region

A branched turnkey optical infrastructure for the region's intelligent security system and a commercial GPON network.

4 253 km of FOCL
Geography
11 districts of Almaty Region
Timeline
October 2024 - September 2025
Client
Freedom Telecom · PPP contract
4 253 km
final FOCL route length
2 508 + 325
video-surveillance sites and hardware-software complexes connected for the «Сергек» system
≈200 000
households - potential GPON coverage
+47%
route growth vs the original plan (2 889 km) - deadlines met
  • 208 new sites integrated, 192 sites relocated at the client's initiative already during construction
  • Soils from category 1 to category 5, an increased share of horizontal directional drilling (HDD)
  • Temporary communication channels for hard-to-reach points: Starlink satellite systems and radio-relay lines
  • Key volumes of C&I works in the ground performed by own mechanized crews

Result The network provides uninterrupted data transmission for the «Сергек» system and became the basis of the region's commercial broadband coverage. Deadlines were met with route growth of more than 1 300 km from the original program.

Cable-laying equipment runs an FOCL route along a road in the autumn steppe of Almaty Region
Route along the road · autumn
A Hidromek excavator digs an FOCL trench on a snow-covered mountain section
Mountain section · winter