Mechanized columns

The work is driven by specialized equipment organized into columns. Depending on conditions and purpose, columns are divided into light and heavy.

Capacity

Five columns, sixteen bulldozers

Bulldozer-based cable layers place cable at a depth of 120 cm. In light soils a heavy column splits into parallel groups - output rises without losing support.

Column Soils Per day Per month
Light column categories 1-2 up to 30 km up to 600 km
Coupled heavy columns categories 3-4 up to 40 km up to 900 km
Heavy column category 5 up to 10 km up to 200 km
Total fleet: 5 columns · 16 bulldozers up to 1 700 km/month

Heavy columns operate regardless of weather. Data: company production program.

Work-process diagram

Five operations, one pass

The field cycle of a mechanized column is part of the full FOCL construction cycle, from survey to handover.

  1. 01

    Route staking

  2. 02

    Trench ripping

  3. 03

    Cable laying

  4. 04

    Backfilling the trench

  5. 05

    Restoring the ground and road

Obstacles

Rivers, roads and difficult sections

Where a column cannot pass, the cable goes under the obstacle or is laid by trench method.

HDD · directional drilling

Drill rigs cover long distances under major obstacles: rivers, woodland, railway beds, parks.

Pipe jacking · bore

Specialized rigs for short crossings: sidewalks, carriageways and other small obstacles.

120 cm

Trench method

For hard-to-reach sections where a bulldozer cannot work. Also: КОД installation, route berming, HDD pits.