Kazakhstan backbone FOCL: western and southern directions
Construction of a backbone FOCL in the ground across eight sections of two directions - in five months.
- Geography
- Western and Southern Kazakhstan
- Timeline
- August - December 2025
- Client
- Freedom Holding · national backbone network
- Mechanized cable laying in the ground to a depth of 120 cm
- Obstacle crossings - HDD and pipe jacking
- Uralsk - Ozinki 105 km
- Zhympity - Uralsk 144 km
- Zhympity - Novonadezhdinka 145 km
- Kobda - Novonadezhdinka 78 km
- Kobda - Aktobe 105 km
- Shelek - Khorgos 208 km
- Shelek - Karkara 15 km
- Ungirtas - Korday 142 km
Result Both directions were handed over as part of the national backbone network; the sections provide exits to the borders in the west and southeast of the country.